New Delhi, April 16: In the face of stiff International Competitive Bidding (ICB), Bharat Heavy Electricals Limited (BHEL) hassecured an order for the renovation and modernisation (R&M) of Electrostatic Precipitators (ESP) at Ramagundam Super Thermal Power Station (STPS).

Valued at Rs.137 Crore, the turnkey order envisages carrying out R&M of ESPs of three units of 200 MW each at RamagundamSTPS, Stage-I (3×200 MW) of NTPC Limited. These ESPs have been in operation for more than 25 years.

Renovation and modernisation of these ESPs will not only facilitate the operation of these units for many more years, but will alsoenable these units to meet the revised emission norms for suspended particulate matter (SPM), notified by the Ministry of Environment, Forest and Climate Change (MOEF & CC) in December, 2015.