Blowout in Gas Well of Oil India Limited at Baghjan, Tinsukia 5th August 2020

Sarkaritel
By Sarkaritel August 5, 2020 17:41

Blowout in Gas Well of Oil India Limited at Baghjan, Tinsukia 5th August 2020


Environmental Impact Assessment

  • TERI Study on Air Quality & Noise Level: Recording of data at already installed analysers and sample collection for monitoring of air quality and noise levelare in progress.
  • TERI study on Bioremediation of Sludge: Application of bio material followed by mechanised tilling is planned from today in the affected areas along the approach road from Plastic Park side to Baghjan blowout well. Application of bio material in farmland, backyard of villager’s houses, nearby water bodies in the affected areas from Baghjan EPS side to blowout wellis alsobeing carried out.Clearing of site prior to bio remediation in wetland areas and site preparations for ex/in-situ bio remediation job in affected areas are also in progress.
  • CSIR-NEIST Seismological Study: Seismological recording carried out by CSIR-NEIST has been completed. Geo-Physical monitoring activities carried out by CSIR- NEIST has also been completed. Data is being analysed for submission of final report.
  • IIT– Guwahati Study on Thermal Mapping & Sonic Measurement:Interpretation of the collected data will be carried out using specialized software at IIT Guwahati and the report will be submitted soon.

Preparation for Capping the Well

  • Final Preparation for Capping Operation:Remaining jobs pertaining to repair and modification of 90ft Athey Wagon like fabrication of alternate Axle including support mechanism to suit the Athey Wagon Unit and modification of secondary section of Athey Wagon Boom are in progress.The civil works for strengthening of the pathway to the cellar at the well site is completed. All efforts are being taken to control the well at the earliest.
  • Final Preparation for Killing Operation:Treatment of well killing fluid is under way.
  • Water Deluge System: All six numbers of High Discharge CMT Water Pumps are operational at site for spraying water to the well head. Out of 08 nos. water transfer pumps, 07 nos. are operational are being used for filling water reservoirs periodically. Modification of suction line of the rest one no. pump is in progress as the water level of Dangori River is receding.

Relief and Rehabilitation

  • Surveyfor Damage Assessment: Survey for assessment of damage for compensation in both Doomdooma and TinsukiaCircle is in progress. Data compilation is being carried out   at the respective circle offices. Total number of families surveyed till 08.2020 both combined in Doomdooma and Tinsukia Circle is 2736.

Law and Order/Bandhs/Blockades etc.

  • Closure of Wells: Production still continues to be affected due to forceful closure of few Oil & Gas wells connected to Baghjan EPS.
  • Blockade at Drilling/Workover Locations: Drilling and workover operation still continue to be affected due to forceful closure of operation at few of the locations.

Impact onOil/GasProduction due to Protests

Due to stoppage/blockades of several producing wells, there was production loss of 652 MT of Crude Oil and 1.53 MMSCM of Natural Gas as reported on 04-08-2020. Cumulative production loss since 27th May, 2020 due to bandhs and blockades: 22112 MT Crude oil, 52.53 MMSCM of natural gas.

Sarkaritel
By Sarkaritel August 5, 2020 17:41