The task was undertaken by the Power Station on a war-footing basis from 03.06.2020 till 06.06.2020 and achieved with the successful synchronizing of Unit-II with the Grid. The rectification work was led by Md. Sajid Akhter, Senior Manager (E&C) and Shri Apurbo Kumar Sarkar, Deputy Manager (Electrical) of the Power Station.
GIS is a compact metal encapsulated Switchgear consisting of components such as Circuit-breakers, Isolators, Earth-switches etc., which can be safely operated in confined spaces wherein Sulphur Hexafluoride (SF6 ) Gas is the insulating medium. Generally, these types of specialized works get outsourced to Original Equipment Manufacturers (OEM) overseas.
In case of NHPC’s TLDP-III Power Station the outsourcing of GIS had been vested to M/s Siemens, Grenoble, France. The delay in confirming the availability of the OEM amid COVID-19 Global Pandemic Lockdown was causing Power Generation loss in Crores of Rupees.