GAIL’s MNJPL Project Almost Complete, to Be Fully Operational by End of 2025

Petronet LNG Force Majeure Notice Stops Gas Supply to GAIL

New Delhi, Sept 24: GAIL (India) Limited is advancing the Mumbai-Nagpur-Jharsuguda pipeline project (MNJPL) as part of India’s National Gas Grid.

Spanning 1,707 km across Maharashtra, Madhya Pradesh, Chhattisgarh, and Odisha, this project has been deemed a high impact initiative under the PM GatiShakti National Master Plan.

Currently, construction is complete in Chhattisgarh, Odisha, and Madhya Pradesh, with only 11 km left in Maharashtra. GAIL expects to fully commission the project by December 31, 2025, following Board approval on September 24, 2025.