BHEL commissions 500 MW Unit in Maharashtra

Sarkaritel
By Sarkaritel April 30, 2015 12:03

BHEL commissions 500 MW Unit in Maharashtra


New Delhi, April 30: Bharat Heavy Electricals Limited (BHEL) has successfully commissioned the first 500 MW unit at the 2×500 MW Chandrapur Super Thermal Power Project (STPP) Stage-III, of Maharashtra State Power Generation Company Limited (MAHAGENCO), in Maharashtra. With this, [8 units aggregating to 2,840 MW] supplied and executed by BHEL are now in operation at Chandrapur STPP.

Work on the second 500 MW unit of Stage-III of the project is going on and the unit is expected to be commissioned in financial year 2015-16.

BHEL’s scope of work in the contract envisaged design, engineering, manufacture, supply, erection and commissioning of Steam Turbines, Generators and Boilers, along with associated Auxiliaries and Electricals, besides state-of-the-art Controls & Instrumentation (C&I) and Electrostatic Precipitators (ESPs).

Significantly, BHEL has been a partner in the power development programme of the state of Maharashtra and has contributed more than 15,000 MW of generating capacity to Maharashtra, the highest in any single state.