Nine Hydroelectric Projects of 2,412 MW capacity commissioned in the North Eastern Region since 2014-15: Union Power and New & Renewable Energy Minister

27hydropower

New Delhi, Dec 10: The Union Minister for Power and New & Renewable Energy has informed about the various policy measures taken by the government to increase or expand power generation capacities / capabilities in the country including North Eastern Region. The details of the same are listed below.

  1. During March, 2019, the Government approved measures to promote hydro power which are detailed below:
  • Declaring Large Hydro Power (LHPs) (> 25 MW projects) as Renewable Energy source.
  • Hydro Purchase Obligation (HPO)
  • Tariff rationalization measures for bringing down hydro power tariff.
  • Budgetary Support for Flood Moderation/Storage Hydro Electric Projects (HEPs).
  • Budgetary Support towards Cost of Enabling Infrastructure, i.e. roads/bridges. The guidelines for Budgetary Support towards Flood Moderation component as well as towards Cost of Enabling Infrastructure have also been notified by Govt. on 28.09.2021.
  • Waiver of Inter State Transmission System (ISTS) Charges on the transmission of power from new Hydro Power Projects would be applicable, for which construction work is awarded and Power Purchase Agreement (PPA) is signed on or before 30.06.2025. Subsequently, part waiver of ISTS charges, in steps of 25% from 01.07.2025 to 01.07.2028, has been extended for HEPs for which construction work is awarded and PPA is signed up to 30.06.2028.

Since year 2014-15, nine Hydroelectric Projects with aggregate installed capacity of 2,412 MW have been commissioned in the North Eastern Region including Sikkim. The details are as under:

Sl. No.NAME OF PROJECTSTATECAPACITY (MW)YEAR OF COMMISSIONING
1JORETHANG LOOPSIKKIM962015
2TEESTA-IIISIKKIM12002017
3TURIALMIZORAM602017
4NEW UMTRUMEGHALAYA402017
5DIKCHUSIKKIM962017
6TASHIDINGSIKKIM972017
7PAREARUNACHAL PRADESH1102018
8KAMENGARUNACHAL PRADESH6002021
9RONGNICHUSIKKIM1132021

Currently, eight hydroelectric projects with aggregate installed capacity of 6,037 MW are under construction in the North Eastern Region of the country. The details are given below.

List of Hydro Electric Projects (above 25 MW) under implementation

Sl. No.Name of ProjectSectorCap. Under   Execution (MW)Estimated Year of Completion
Arunachal Pradesh   
1Subansiri LowerCentral                     2,0002023-26        (May’25)##
2Dibang Multipurpose ProjectCentral                     2,8802031-32
(Feb’32)
Assam   
3Lower KopliState                        1202024-25  
(Mar’25)
Sikkim   
4Teesta St. VICentral                        5002026-27     
(Aug’26)
5Rangit-IVCentral                        1202024-25              (Aug’24)
6*BhasmeyPrivate                          51*
7*Rangit-IIPrivate                          66*
8*PananPrivate                        300*
##:  2 units (500 MW) likely during 2023-24, 4 units (1,000 MW) during 2024-25 and remaining 2 units (500 MW) during 2025-26
* The project is presently stalled.

Further, as per Section 8 (1) of the Electricity Act, 2003, any generating company intending to set up a hydro generating station shall prepare and submit to the Authority for its concurrence, a scheme estimated to involve a capital expenditure exceeding such sum (presently, ₹ 1,000 crores), as may be fixed by the Central Government, from time to time, by notification.

Accordingly, Central Electricity Authority (CEA) accorded concurrence to 17 Hydro Electric Schemes (14,589 MW) in North Eastern Region including Sikkim. The details are given below:

Sl. No.Name of SchemeStateInstalled Capacity (MW)Estimated Year of Completion
 TEESTA ST-IVSikkim5202031-32
 TAWANG ST-IArunachal Pradesh600Beyond 2031-32
 WAH-UMIAM STAGE-IIIMeghalaya852029-30
 TAWANG ST-IIArunachal Pradesh800Beyond 2031-32
 HEOArunachal Pradesh2402028-29
 TATO-IArunachal Pradesh1862028-29
 TATO-IIArunachal Pradesh700Beyond 2031-32
 DEMWE LOWERArunachal Pradesh17502031-32
 KALAI-IIArunachal Pradesh1200Beyond 2031-32
 TALONG LONDAArunachal Pradesh2252031-32
 ETALINArunachal Pradesh3,0972030-31
 NAFRAArunachal Pradesh1202027-28
 HIRONGArunachal Pradesh500Beyond 2031-32
 NAYING Arunachal Pradesh1,000Beyond 2031-32
 ATTUNLIArunachal Pradesh6802030-31
 LOWER SIANGArunachal Pradesh2,700Beyond 2031-32
 DIKHUNagaland1862030-31

This information has been given by the Union Minister for Power and New & Renewable Energy R. K. Singh, in a written reply to a question, in Lok Sabha.